Morning board
Today's assignment
Thursday, Jan 1 · Douglas Wiebe
Crew 1 · start 07:00
Peace River — 100 St curb & sidewalk
Project
Peace River — 100 St curb & sidewalk100 St & 98 Ave, Peace River ABCurb and gutter pour at 98 Ave — form check, 32 MPa placement, finish and cure blankets.
Equipment assigned
MX-11
MX-14
PK-06
Crew — 5 on site
Trevor Wieler (lead foreman)Curtis Bergen · Wesley Zacharias+ 2 swampers
Dispatch note
First load leaves the plant at 07:15 — confirm slump and air on arrival. Cylinders required on this pour.
Start day: open FLHA
Hazard assessment before the first shovel — signed on the tailgate.