Ruel Concrete LtdRuel Concrete Crew Portal

Morning board

Today's assignment

Thursday, Jan 1 · Douglas Wiebe

Crew 1 · start 07:00

Peace River — 100 St curb & sidewalk

Project

Peace River — 100 St curb & sidewalk100 St & 98 Ave, Peace River ABCurb and gutter pour at 98 Ave — form check, 32 MPa placement, finish and cure blankets.

Equipment assigned

MX-11
MX-14
PK-06

Crew — 5 on site

Trevor Wieler (lead foreman)Curtis Bergen · Wesley Zacharias+ 2 swampers

Dispatch note

First load leaves the plant at 07:15 — confirm slump and air on arrival. Cylinders required on this pour.
Start day: open FLHA

Hazard assessment before the first shovel — signed on the tailgate.

Tomorrow — Friday, Jan 2

Draft — office planning

Peace River — 100 St curb & sidewalk

Crew 1 · start 07:00 · MX-11, MX-14, PK-06